Project programme

From consultation to delivery.

Follow the anticipated milestones for feedback, planning, construction and the first new homes at Boyd Park.

3 Completed
7 Upcoming
Next milestone Reserved Matters application submission

Milestones

  1. Completed

    Outline planning permission

    The broad principle of development at Boyd Park has already been agreed.

    Planning

    Outline planning permission

    Completed

    The broad principle of development at Boyd Park has already been agreed.

    Read the proposal for information about the phase covered by this consultation.

    Related information →
  2. Completed

    Public consultation (phase 2) completed

    Public consultation for phase 2 completed in September 2026.

    Consultation
  3. Completed

    Public exhibition at Abingdon Town Hall

    Tuesday 15 September, 2pm to 9pm at Abingdon Town Hall, Market Place, Abingdon OX14 3HG.

    Consultation

    Public exhibition at Abingdon Town Hall

    Completed

    Tuesday 15 September, 2pm to 9pm at Abingdon Town Hall, Market Place, Abingdon OX14 3HG.

    Illustrative Boyd Park homes
  4. Current

    Reserved Matters application submission

    Phase 2 Reserved Matters application submission is expected in Autumn 2026.

    Application

    Reserved Matters application submission

    Current

    Phase 2 Reserved Matters application submission is expected in Autumn 2026.

    What does this milestone mean?

    The project team expects to submit the Reserved Matters application for this phase in Autumn 2026. This is an anticipated date and may change.

    Where can I explore the proposals?

    The proposal, storyboard and documents pages explain the phase covered by this consultation.

    How can I follow progress?

    Check the project news and timeline for updates from the project team.

  5. Upcoming

    Consultation closes

    Please submit comments by Thursday 22 October 2026.

    Consultation
  6. Upcoming

    Reserved Matters planning permission

    Reserved Matters planning permission is expected in Spring 2027.

    Planning
  7. Upcoming

    Validation and statutory consultation

    Validation and statutory consultation are expected in Summer 2027.

    Planning
  8. Upcoming

    Construction commences

    Construction is expected to commence in Autumn 2027.

    Delivery
  9. Upcoming

    First occupations

    First occupations are indicated for Autumn 2028, with overall completion in 2030.

    Delivery
  10. Upcoming

    Overall completion

    Overall completion is expected in 2030.

    Delivery